Reconstruction of a local street in the village of Vasilevo next to a water canal

Active
Budget

2857587.00mkd

Length

420,0m

Width of existing dirt road

3,5m

Width of new asphalt road

3,5m

With this sub-project is planned reconstruction of the existing dirt road.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing dirt layer, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16 – 7,0 sm
  6. Installing curb/edge concrete elements
  7. Installing pipes for fiber optic cable.
  8. Mapping with horizontal and vertical signalization.

Gallery

Situation

Before the start of construction works
After completion of construction works