Реконструкција на улица,,Улица 3” во н.м. Дорфулија- Општина Лозово

Active
Budget

3059333mkd

Length

(MK) 299

Total road length: L = 299 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.

The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 3,059,333  denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes and replacing the covers
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs

Gallery

Picture2

01-01-1970

Picture1

01-01-1970

Situation

Before the start of construction works
https://www.mapillary.com/app/?lat=41.76622987942923&lng=21.894302751204577&z=17.116295796373215&mapStyle=Esri+satellite&pKey=2214937018702300
After completion of construction works
https://www.mapillary.com/app/?lat=41.76622987942923&lng=21.894302751204577&z=17.116295796373215&mapStyle=Esri+satellite&pKey=716958676956408

GRIEVANCE REDRESS MECHANISM

file a complaint