Reconstruction of street Disanska

Active
Budget

4746400mkd

Length

324.00m

Width of asphalt road

6,0m

Sidewalk (one side)

1x2,00m

With this sub-project is planned reconstruction of the existing asphalt road and sidewalk.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Scratching the existing layer of asphalt.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 22cA-8,0sm
    2. Layer of AB 11c – 5,0sm
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing curb/edge concrete elements
  8. Leveling the existing manholes
  9. Constructing sidewalks with paver elements.
  10. Mapping with horizontal and vertical signalization

Gallery

Situation

Before the start of construction works
After completion of construction works