Reconstruction of Local Road in Novo Vladevci – Staro Vladevci

Active
Budget

13288064.00mkd

Length

1.761m

Width of asphalt road

3,5m

With this sub-project is planned reconstruction of the existing asphalt road.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16 – 7,0 sm
  6. Installing curb/edge concrete elements
  7. Constructing access culvert.
  8. Mapping with horizontal and vertical signalization.