Width of asphalt road
6,0m2
Sidewalks (two sides)
2 x 1,0m
With this sub-project is planned reconstruction of the existing asphalt road, and sidewalks
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Scratching the existing layer of asphalt
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16a -4,5sm
- Spraying with bituminized emulsion in between the layers.
- Installing curb/edge concrete elements
- Constructing sidewalks with paver elements.
- Leveling the existing manholes
- Mapping with horizontal and vertical signalization.