Reconstruction of local street Marshal Tito

Active
Budget

2991234mkd

Length

195.00m

Width of existing dirt road

4,5m -5,5m

Sidewalk (two sides)

0,5 - 1,5m


Width of new planned asphalt road

4,5 - 5,5m

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing dirt layer, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed.
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16 – 8sm
  6. Installing curb/edge concrete elements
  7. Leveling the existing manholes and constructing new manholes where needed.
  8. Constructing sidewalks with paver elements.
  9. Installing pipes for fiber optic cable.
  10. Constructing pipes for drainage the storm water to the recipient
  11. 11. Mapping with horizontal and vertical signalization.