                                        Width of existing dirt road
                                        4,5m- 5,5m
                                     
                                    
                                        Sidewalk (one side)
                                        1 x 1,5m
                                     
                                 
                                
                                                                
                                
                                    
                                        Width of new planned asphalt road
                                        5,5m
                                     
                                                                      
                                                                   
                                                              
                                                                
                                
                                
                            
                         
                      
                        
                            
With this sub-project is planned reconstruction of the existing dirt road and constructing a new sidewalk.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Removing the existing dirt layer, the existing base course and part of the subgrade.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16 – 8sm
 
- Installing curb/edge concrete elements
- Constructing sidewalk with paver elements.
- Mapping with horizontal and vertical signalization.