Reconstruction of Krushevska street

Active
Budget

16981626mkd

Length

1,318.53m

Width of asphalt road

4,5m - 7,5m

Sidewalk (two sided)

W=1,0m -2,0m

With this sub-project is planned reconstruction of the existing asphalt road and the sidewalks

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Scratching the existing layer of asphalt
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16 -7sm
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing curb/edge concrete elements
  8. Reconstructing the existing sidewalk with paver elements.
  9. Leveling the existing manholes, constructing surface channel, pipes for drainage the storm water to the recipient
  10. Mapping with horizontal and vertical signalization
  11. Electrical installations (according to project for electrical installations)

Gallery

ул.Крушевска (005)

10-10-2021

viber_image_2021-10-25_12-16-10-554

25-10-2021

viber_image_2021-10-23_15-51-49-964

23-10-2021

viber_image_2021-10-23_12-26-28-774

23-10-2021

viber_image_2021-10-23_12-26-28-444

23-10-2021

viber_image_2021-10-23_12-00-57-635

23-10-2021

viber_image_2021-10-21_15-44-06-261

21-10-2021

viber_image_2021-10-20_10-19-57-052

20-10-2021

viber_image_2021-10-19_14-58-09-105

19-10-2021

viber_image_2021-10-19_10-34-17-126

19-10-2021

viber_image_2021-10-18_14-50-19-337

18-10-2021

viber_image_2021-10-18_10-04-39-443

18-10-2021

viber_image_2021-10-11_13-32-31-928

11-10-2001

viber_image_2021-10-01_13-16-32-914

01-10-2021

Situation

Before the start of construction works
After completion of construction works

Documents

GRIEVANCE REDRESS MECHANISM

file a complaint