Local Street Anton Keckarov – Gjorce Petrov

Active
Budget

4612111mkd

Length

420.00m

Width of asphalt road

4,0m - 5,5m

With this sub-project is planned reconstruction of the existing asphalt road. With the reconstruction are planned the next activities:

  1. Removing the existing surface course, the existing base course and part of the subgrade, removing the existing sidewalks.
  2. Marking the route of the new planned sub – project.
  3. Leveling, planning and compacting subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed.
  5. Constructing two layers of asphalt:
    • binder course
    • wearing course
  6. Spraying with bituminized emulsion in between the layers.
  7. Leveling the existing manholes.
  8. Mapping with horizontal and vertical signalization

Gallery

1

11-05-2021

3

11-05-2021

13

11-05-2021

5

11-05-2021

4

11-05-2021

6

25-05-2021

12

26-05-2021

11

26-05-2021

8

26-05-2021

7

26-05-2021

10

28-05-2021

9

26-05-2021

17

11-06-2021

21

11-06-2021

19

11-06-2021

16

11-06-2021

15

11-06-2021

18

11-06-2021

24

11-06-2021

Situation

Before the start of construction works
After completion of construction works

GRIEVANCE REDRESS MECHANISM

file a complaint