Reconstruction of local street Makedonski Prosvetiteli

Active
Budget

33050304mkd

Length

420.0m

Width of asphalt road

2х3,25m

Sidewalk (two sides)

2m


Bike path

1х2,4m

Parking space

4,5m

With this sub-project is planned reconstruction of the existing asphalt road, the sidewalks and construction a parking place and new bike path. With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing one layer of asphalt and granite blocks
    1. Bituminized asphalt layer BNS 16-7,0sm
    2. Granit blocks 10/10
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing curb/edge concrete elements
  8. Leveling the existing manholes and constructing new manholes and channels for drainage of storm water.
  9. Constructing sidewalk with granite blocks.
  10. Constructing bike path with granite blocks.
  11. Electrical installations
  12. Mapping with horizontal and vertical signalization.

Gallery

Situation

Before the start of construction works
After completion of construction works

Documents

GRIEVANCE REDRESS MECHANISM

file a complaint