With this sub-project is planned reconstruction of the existing asphalt road and the existing sidewalks. With the reconstruction are planned the next activities:
- Marking the route of the new planned sub – project.
- Scratching the existing wearing course.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing two layers of asphalt:
- binder course
- wearing course
- Spraying with bituminized emulsion in between the layers.
- Installing a curb/edge concrete element.
- Reconstruction of existing sidewalks with paver elements.
- Leveling the existing manholes.
- Installing pipes for optical cable.
- Mapping with horizontal and vertical signalization.
With this sub-project is planned reconstruction of the existing asphalt road and the existing sidewalks. With the reconstruction are planned the next activities:
- Marking the route of the new planned sub – project.
- Scratching the existing wearing course.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing two layers of asphalt:
- binder course
- wearing course
- Spraying with bituminized emulsion in between the layers.
- Installing a curb/edge concrete element.
- Reconstruction of existing sidewalks with paver elements.
- Leveling the existing manholes.
- Installing pipes for optical cable.
- Mapping with horizontal and vertical signalization.