Reconstruction of Local Street: Access Road to Health-Emergency Centre in Kratovo

With this sub-project is planned reconstruction of  the existing   asphalt road and the existing sidewalks. With the reconstruction are planned the next activities:

  1. Marking the route of the new planned sub – project.
  2. Scratching the existing wearing course.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed.
  5. Constructing two layers of asphalt:
    • binder course
    • wearing course
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing a curb/edge concrete element.
  8. Reconstruction of existing sidewalks with paver elements.
  9. Leveling the existing manholes.
  10. Installing pipes for optical cable.
  11. Mapping with horizontal and vertical signalization.

With this sub-project is planned reconstruction of  the existing   asphalt road and the existing sidewalks. With the reconstruction are planned the next activities:

  1. Marking the route of the new planned sub – project.
  2. Scratching the existing wearing course.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed.
  5. Constructing two layers of asphalt:
    • binder course
    • wearing course
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing a curb/edge concrete element.
  8. Reconstruction of existing sidewalks with paver elements.
  9. Leveling the existing manholes.
  10. Installing pipes for optical cable.
  11. Mapping with horizontal and vertical signalization.