Total road length: L = 1320 m
- Design speed: 30 km/h
- Road profile width: 00 m
- Maximum cross slope: 50 %
- Maximum longitudinal slope: 69 %
Pavement Structure
- BNHS 16 – asphalt layer: d = 7cm
- Base layer of buffer layer under the roadway: 35cm
- Base layer of buffer layer under the sidewalks: 20cm
The subject street is part of Т4D5.The work is being carried out by the construction DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 16,421,768 denars.
Project Overview
Preparatory work:
- Securing and marking the route
Lower and upper structure:
- Mechanical excavation of humus, with transport to the landfill (for road widening)
- Mechanical excavation of the existing roadway
- Subsoil/bed preparation
- Embankment preparation
- Installation of a buffer layer (under the roadway) d=35cm
- Installation of concrete curbs 18/24
- Installation of buffer layer (under sidewalks) d=20cm
- Installation of BNHS layer 16 d=8cm
- Installation of sidewalk concrete curbs 8/22
- Installation of paver elements on sidewalks d=6cm
Drainage:
- Installation of drainage pipes f150 (with excavation, filter material and backfilling
- Drainage from km.0+902-1+32
Traffic signals:
- Installation of traffic signs
- Marking of horizontal signaling
Additional quantities:
- Construction of an embankment, with procurement of the material (improved subgrade)
- Construction of two drainage outlets at km.0+958 and km.1+026 in accordance with the technical solution for road drainage.
With this sub-project is planned reconstruction of the existing dirt road.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Removing the existing dirt layer, the existing base course and part of the subgrade.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16 – 7,0 sm
- Installing curb/edge concrete elements
- Installing pipes for fiber optic cable.
- Mapping with horizontal and vertical signalization.
With this sub-project is planned reconstruction of the existing dirt road.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Removing the existing dirt layer, the existing base course and part of the subgrade.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16 – 7,0 sm
- Installing curb/edge concrete elements
- Installing pipes for fiber optic cable.
- Mapping with horizontal and vertical signalization.
With this sub-project is planned reconstruction of the existing asphalt road.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16 – 7,0 sm
- Installing curb/edge concrete elements
- Constructing access culvert.
- Mapping with horizontal and vertical signalization.