Reconstruction of a local road from the intersection with the road to dam Turija to the center of the village of Dobrosinci-Municipality of Vasilevo

Total road length: L = 1320 m

  • Design speed: 30 km/h
  • Road profile width: 00 m
  • Maximum cross slope: 50 %
  • Maximum longitudinal slope: 69 %

Pavement Structure

  • BNHS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 35cm
  • Base layer of buffer layer under the sidewalks: 20cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 16,421,768 denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of humus, with transport to the landfill (for road widening)
  • Mechanical excavation of the existing roadway
  • Subsoil/bed preparation
  • Embankment preparation
  • Installation of a buffer layer (under the roadway) d=35cm
  • Installation of concrete curbs 18/24
  • Installation of buffer layer (under sidewalks) d=20cm
  • Installation of BNHS layer 16 d=8cm
  • Installation of sidewalk concrete curbs 8/22
  • Installation of paver elements on sidewalks d=6cm

Drainage:

  • Installation of drainage pipes f150 (with excavation, filter material and backfilling
  • Drainage from km.0+902-1+32

Traffic signals:

  • Installation of traffic signs
  • Marking of horizontal signaling

Additional quantities:

  • Construction of an embankment, with procurement of the material (improved subgrade)
  • Construction of two drainage outlets at km.0+958 and km.1+026 in accordance with the technical solution for road drainage.

Reconstruction of a local street in the village of Vasilevo next to a water canal

With this sub-project is planned reconstruction of the existing dirt road.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing dirt layer, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16 – 7,0 sm
  6. Installing curb/edge concrete elements
  7. Installing pipes for fiber optic cable.
  8. Mapping with horizontal and vertical signalization.

Reconstruction of local street in v.Gradoshorci

With this sub-project is planned reconstruction of the existing dirt road.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing dirt layer, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1.     Bituminized asphalt layer BNS 16 – 7,0 sm
  6. Installing curb/edge concrete elements
  7. Installing pipes for fiber optic cable.
  8. Mapping with horizontal and vertical signalization.

Reconstruction of Local Road in Novo Vladevci – Staro Vladevci

With this sub-project is planned reconstruction of the existing asphalt road.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16 – 7,0 sm
  6. Installing curb/edge concrete elements
  7. Constructing access culvert.
  8. Mapping with horizontal and vertical signalization.