Municipality of activity: Kavadarci Municipality
Reconstruction of streets Goce Delcev
Reconstruction of street Zapaden Bulevar
With this sub-project is planned reconstruction of the existing asphalt road.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Scratching the existing layer of asphalt
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 22cA-8,0sm
- Layer of AB 11c – 5,0sm
- Spraying with bituminized emulsion in between the layers.
- Installing curb/edge concrete elements
- Leveling the existing manholes
- Mapping with horizontal and vertical signalization.
Reconstruction of street Disanska
With this sub-project is planned reconstruction of the existing asphalt road and sidewalk.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Scratching the existing layer of asphalt.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 22cA-8,0sm
- Layer of AB 11c – 5,0sm
- Spraying with bituminized emulsion in between the layers.
- Installing curb/edge concrete elements
- Leveling the existing manholes
- Constructing sidewalks with paver elements.
- Mapping with horizontal and vertical signalization
Reconstruction of street Ilindenska
With this sub-project is planned reconstruction of the existing asphalt road and part of the street sidewalks. With the reconstruction are planned the next activities:
- Removing the existing surface course, the existing base course and part of the subgrade, removing the existing sidewalks.
- Marking the route from the surveyor from the new planned sub – project.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing two layers of asphalt:
- binder course
- wearing course
- Spraying with emulsion in between the layers.
- Installing a curb/edge concrete element.
- Reconstruction of existing sidewalks with paver elements.
- Leveling the existing manholes.
- Installing pipes for optical cable.
- Mapping with horizontal and vertical signalization.
Reconstruction of street Pionerska
With this sub-project is planned reconstruction of the existing asphalt road. With the reconstruction are planned the next activities:
- Marking the route of the new planned sub – project.
- Scratching the existing wearing course.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing two layers of asphalt:
- binder course
- wearing course
- Spraying with bituminized emulsion in between the layers.
- Installing a curb/edge concrete element.
- Leveling the existing manholes.
- Installing pipes for optical cable.
- Mapping with horizontal and vertical signalization.
Reconstruction of street Brakja Dzunovi
With this sub-project is planned reconstruction of the existing asphalt road.With the reconstruction are planned the next activities:
- Marking the route of the new planned sub – project
- Scratching the existing wearing course.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing two layers of asphalt
- binder course
- wearing course
- Spraying with bituminized emulsion in between the layers.
- Installing a curb/edge concrete elements
- Leveling the existing manholes
- Installing pipes for optical cable
- Mapping with horizontal and vertical signalization