With this sub-project is planned reconstruction of the existing dirt road and constructing new sidewalks.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Removing the existing dirt layer, the existing base course and part of the subgrade.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16-7,0sm
- Layer of AB 11 – 4,0sm
- Installing curb/edge concrete elements
- Leveling the existing manholes and constructing new manholes and channels for drainage of storm wather.
- Constructing sidewalks with paver elements.
- Installing pipes for fiber optic cable.
- Mapping with horizontal and vertical signalization.