Construction of local road,, Street 4”- Municipality of Sveti Nikole

Total road length: L = 101.08 m

  • Design speed: 30 km/h
  • Road profile width: 50 m
  • Maximum cross slope: 50 %
  • Maximum longitudinal slope: 83%

Pavement Structure

  • BNHS 22 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30cm
  • Base layer of buffer layer under the sidewalks: 20cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 2,556,580 denars.

Project Overview

Preparatory work:

  • Securing and marking the route
  • Dislocation of existing concrete columns

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making a bed
  • Making an embankment
  • Leveling existing manholes
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of concrete curbs18/24
  • Installation of buffer layer (under sidewalks) d=20см.
  • Installation of BNS22 layer d=7см.
  • Installation of AB11 layer d=5см.
  • Installation of sidewalk concrete curbs 6/20
  • Installation of paver elements on sidewalks

Drainage:

  • Installation of drainage pipes f150 (with excavation, filter material and backfilling
  • Procurement and installation of street drains
  • Production of absorption wells (4 pcs.)

Traffic signals:

  • Installation of traffic signs
  • Marking of horizontal signaling

Additional quantities:

  • Construction of an embankment, with procurement of the material (improved bedding)
  • Procurement and installation of iron manhole covers

Construction of local road,, Street 3”- Municipality of Sveti Nikole

Total road length: L = 98.02 m

  • Design speed: 30 km/h
  • Road profile width: 50 m
  • Maximum cross slope: 50 %
  • Maximum longitudinal slope: 83%

Pavement Structure

  • BNHS 22 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30cm
  • Base layer of buffer layer under the sidewalks: 20cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 2,846,182 denars.

Project Overview

Preparatory work:

  • Securing and marking the route
  • Dislocation of existing concrete columns

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making a bed
  • Making an embankment
  • Leveling existing manholes
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of concrete curbs18/24
  • Installation of buffer layer (under sidewalks) d=20см.
  • Installation of BNS22 layer d=7см.
  • Installation of AB11 layer d=5см.
  • Installation of sidewalk concrete curbs 6/20
  • Installation of paver elements on sidewalks

Drainage:

  • Installation of drainage pipes f150 (with excavation, filter material and backfilling
  • Procurement and installation of street drains
  • Production of absorption wells (4 pcs.)

Traffic signals:

  • Installation of traffic signs
  • Marking of horizontal signaling

Additional quantities:

  • Construction of an embankment, with procurement of the material (improved bedding)
  • Procurement and installation of iron manhole covers

Construction of local road ,,Mihajlo Apostoloski”- Municipality of Sveti Nikole

Total road length: L = 356.98 m

  • Design speed: 30 km/h
  • Road profile width: 50 m
  • Maximum cross slope: 50 %
  • Maximum longitudinal slope: 5.30 %

Pavement Structure

  • BNHS 22 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30cm
  • Base layer of buffer layer under the sidewalks: 20cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 9,095,148 denars.

Project Overview

Preparatory work:

  • Securing and marking the route
  • Dislocation of existing concrete columns

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making a bed
  • Making an embankment
  • Leveling existing manholes
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of concrete curbs18/24
  • Installation of buffer layer (under sidewalks) d=20см.
  • Installation of BNS22 layer d=7см.
  • Installation of AB11 layer d=5см.
  • Installation of sidewalk concrete curbs 6/20
  • Installation of paver elements on sidewalks

Drainage:

  • Installation of drainage pipes f150 (with excavation, filter material and backfilling
  • Procurement and installation of street drains
  • Production of absorption wells (4 pcs.)

Traffic signals:

  • Installation of traffic signs
  • Marking of horizontal signaling

Additional quantities:

  • Construction of an embankment, with procurement of the material (improved bedding)
  • Procurement and installation of iron manhole covers

Construction of local road,, Gavrilo Gavrilski”- Municipality of Sveti Nikole

Total road length: L = 332.84 m

  • Design speed: 30 km/h
  • Road profile width: 50 m
  • Maximum cross slope: 50 %
  • Maximum longitudinal slope: 35%

Pavement Structure

  • BNHS 22 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30cm
  • Base layer of buffer layer under the sidewalks: 20cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 7,840,222 denars.

Project Overview

Preparatory work:

  • Securing and marking the route
  • Dislocation of existing concrete columns

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making a bed
  • Making an embankment
  • Leveling existing manholes
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of concrete curbs18/24
  • Installation of buffer layer (under sidewalks) d=20см.
  • Installation of BNS22 layer d=7см.
  • Installation of AB11 layer d=5см.
  • Installation of sidewalk concrete curbs 6/20
  • Installation of paver elements on sidewalks

Drainage:

  • Installation of drainage pipes f150 (with excavation, filter material and backfilling
  • Procurement and installation of street drains
  • Production of absorption wells (4 pcs.)

Traffic signals:

  • Installation of traffic signs
  • Marking of horizontal signaling

Additional quantities:

  • Construction of an embankment, with procurement of the material (improved bedding)
  • Procurement and installation of iron manhole covers