Reconstruction of a local road from the intersection with the road to dam Turija to the center of the village of Dobrosinci-Municipality of Vasilevo

Active
Budget

16421768mkd

Length

1320

Total road length: L = 1320 m

  • Design speed: 30 km/h
  • Road profile width: 00 m
  • Maximum cross slope: 50 %
  • Maximum longitudinal slope: 69 %

Pavement Structure

  • BNHS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 35cm
  • Base layer of buffer layer under the sidewalks: 20cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 16,421,768 denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of humus, with transport to the landfill (for road widening)
  • Mechanical excavation of the existing roadway
  • Subsoil/bed preparation
  • Embankment preparation
  • Installation of a buffer layer (under the roadway) d=35cm
  • Installation of concrete curbs 18/24
  • Installation of buffer layer (under sidewalks) d=20cm
  • Installation of BNHS layer 16 d=8cm
  • Installation of sidewalk concrete curbs 8/22
  • Installation of paver elements on sidewalks d=6cm

Drainage:

  • Installation of drainage pipes f150 (with excavation, filter material and backfilling
  • Drainage from km.0+902-1+32

Traffic signals:

  • Installation of traffic signs
  • Marking of horizontal signaling

Additional quantities:

  • Construction of an embankment, with procurement of the material (improved subgrade)
  • Construction of two drainage outlets at km.0+958 and km.1+026 in accordance with the technical solution for road drainage.

Gallery

Picture1

01-01-1970

Picture2

01-01-1970

Picture3

01-01-1970

Picture4

01-01-1970

Picture6

01-01-1970

Picture7

01-01-1970

Picture8

01-01-1970

Picture9

01-01-1970

Picture10

01-01-1970

Picture12

01-01-1970

Picture11

01-01-1970

Picture13

01-01-1970

Picture17

01-01-1970

Picture15

01-01-1970

Picture5

01-01-1970

Picture16

01-01-1970

Picture14

01-01-1970

Situation

Before the start of construction works
https://www.mapillary.com/app/?lat=41.523263618541506&lng=22.661412597610934&z=17.827293723730737&pKey=1270331077373036
After completion of construction works
https://www.mapillary.com/app/?lat=41.523129068207&lng=22.660889727206&z=17&pKey=3579511898927919

GRIEVANCE REDRESS MECHANISM

file a complaint