Width of asphalt road
6,0m
Existing sidewalks (one side)
W=1,5m
With this sub-project is planned reconstruction of the existing part of asphalt road and sidewalk.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 22 -6,0sm
- Layer of AB 16 – 6sm
- Spraying with bituminized emulsion in between the layers.
- Installing curb/edge concrete elements
- Constructing sidewalk with paver elements.
- Constructing surface earth channels, pipes for drainage the storm water to the recipient
- Mapping with horizontal and vertical signalization