Active
Width of asphalt road
4,0m
Sidewalk (one side)
W=1,0m
With this sub-project is planned reconstruction of the existing asphalt road and sidewalks.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- 2 Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16 – 7,0 sm
- Installing curb/edge concrete elements.
- Constructing sidewalks with paver elements.
- Leveling the existing manholes.
- Mapping with horizontal and vertical signalization.