Active
Width of asphalt road
6,0m
Sidewalk (one side)
3,00m
With this sub-project is planned reconstruction of the existing asphalt road (crossroad) and sidewalks.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 22 -12,0sm
- Layer of AB 11 – 4sm
- Spraying with bituminized emulsion in between the layers.
- Installing curb/edge concrete elements
- Constructing sidewalks with paver elements.
- Leveling the existing manholes
- Constructing pipes for drainage the storm water.
- Electrical installations.
- Mapping with horizontal and vertical signalization