Reconstruction of street Antigona to D. Mircev

Active
Budget

16719230mkd

Length

1190.00m

Traffic lane

2x2.00=4.00m

Sidewalks

2x1.00=2.00m


Traffic lane

2x3.00=6.00m

Sidewalks

1.00-1.50m


Traffic lane

2x3.00=6.00m

Sidewalks

2x1.00=2.00m


Traffic lane

2x1.60=3.20m

Sidewalks

1.00m

With this sub-project is planned reconstruction of the existing asphalt road and sidewalks. With the reconstruction are planned the next activities:

  1. Removing the existing surface course , the existing base course and part of the subgrade, removing the existing sidewalks.
  2. Marking the route from the surveyor from the new planned sub – project.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing two layers of asphalt
    • binder  course
    • wearing course
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing a curb/edge concrete elements
  8. Reconstruction of existing sidewalks with paver elements
  9. Leveling the existing manholes
  10. Installing pipes for optical cable
  11. Mapping with horizontal and vertical signalization

Gallery

Situation

Before the start of construction works
After completion of construction works