Width of asphalt road
7,0m
Sidewalks (one side)
2,5m - 5,0m
With this sub-project is planned reconstruction of the existing part of the road – the wearing course and the sidewalk. With the reconstruction are planned the next activities:
- Marking the route of the new planned sub – project.
- Scratching the existing wearing course.
- Leveling, planning and compacting subgrade until needed.
- Leveling and compacting base course with crushed stone until needed.
- Constructing two layers of asphalt:
- binder course
- wearing course
- Spraying with bituminized emulsion in between the layers.
- Reconstruction of the existing sidewalk with paver elements.
- Installing a curb/edge concrete element.
- Leveling the existing manholes.
- Mapping with horizontal and vertical signalization