Reconstruction of local road,, Street 16” in Karatmanovo- Municipality of Lozovo

Active
Budget

432169mkd

Length

72

Total road length: L = 72 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 432,169 denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs

Gallery

Picture1

01-01-1970

Picture2

01-01-1970

Situation

Before the start of construction works
https://www.mapillary.com/app/?lat=41.762415446170706&lng=21.87109168299719&z=17.757060940340867&pKey=1025103818415950&mapStyle=Esri+satellite
After completion of construction works
https://www.mapillary.com/app/?lat=41.76244710811784&lng=21.871044441652543&z=19.556449001311233&pKey=1553499895497889&mapStyle=Esri+satellite