Reconstruction of local road,, Street 8” in Dorfulija- Municipality of Lozovo

Total road length: L = 112 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 719,332 denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes and replacing the covers
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs

Reconstruction of local road,, Street 7” in Dorfulija- Municipality of Lozovo

Total road length: L = 144 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 848,839 denars.

Project Overview

 Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes and replacing the covers
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs

Reconstruction of local road,, Street 6” in Dorfulija- Municipality of Lozovo

Total road length: L = 254 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 1,373,615 denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes and replacing the covers
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs

Reconstruction of local road,, Street 5” in Dorfulija- Municipality of Lozovo

Total road length: L = 136 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 607,367 denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes and replacing the covers
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs

Reconstruction of local road,, Street 4” in Dorfulija- Municipality of Lozovo

Total road length: L = 226 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 1,563,605 denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes and replacing the covers
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs

Реконструкција на улица,,Улица 3” во н.м. Дорфулија- Општина Лозово

Total road length: L = 299 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.

The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 3,059,333  denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes and replacing the covers
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs

Reconstruction of local road,, Street 2” in Dorfulija- Municipality of Lozovo

Total road length: L = 299 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 1,261,462 denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes and replacing the covers
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs

 

Reconstruction of local road,, Street 12” in Karatmanovo- Municipality of Lozovo

Total road length: L = 133 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 780,161denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs

Reconstruction of local road,, Street 18” in Karatmanovo- Municipality of Lozovo

Total road length: L = 67 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 347,644 denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs

Reconstruction of local road,, Street 16” in Karatmanovo- Municipality of Lozovo

Total road length: L = 72 m

  • Design speed: 30 km/h
  • Road profile width: 3.50 m

Pavement Structure

  • BNS 16 – asphalt layer: d = 7cm
  • Base layer of buffer layer under the roadway: 30 cm

The subject street is part of Т4D5.The work is being carried out by the construction  DPTU ЕSKAVATORI – MK Dooel Skopje. The value of the signed contract is 432,169 denars.

Project Overview

Preparatory work:

  • Securing and marking the route

Lower and upper structure:

  • Mechanical excavation of earth in a wide excavation 3-4 floors.
  • Making subsoil/ bedding
  • Making an embankment (improved bedding 15 cm)
  • Leveling existing manholes
  • Installing a buffer layer (under the roadway)d=30см
  • Installation of BNHS 16 layer d=7см.
  • Construction of banks 0.5 cm

Traffic signals:

  • Installation of traffic signs