Reconstruction of local street Novoproektirana

With this sub-project is planned reconstruction of the existing asphalt road and sidewalks.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. 2 Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16 – 7,0 sm
  6. Installing curb/edge concrete elements.
  7. Constructing sidewalks with paver elements.
  8. Leveling the existing manholes.
  9. Mapping with horizontal and vertical signalization.

Reconstruction of local street Ce Gevara

With this sub-project is planned reconstruction of the existing asphalt road and sidewalks.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16 – 7,0 sm
  6. Installing curb/edge concrete elements.
  7. Constructing sidewalks with paver elements.
  8. Leveling the existing manholes.
  9. Mapping with horizontal and vertical signalization.