Active 
                        
                                                                        
                                                      
                                                                                
                          
                            
                                
                                    
                                        Width of the new planned asphalt road
                                        Brunch 1 – 4,0m - Brunch 2 – 3,5m
                                     
                                    
                                 
                                
                                                                
                                                                
                                
                                
                            
                         
                      
                        
                            
With this sub-project is planned reconstruction of the existing asphalt road and sidewalk.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
 
- Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
 
- Leveling, planning and compacting the subgrade until needed.
 
- Leveling and compacting the base course with crushed stone until needed.
 
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16A -7sm
 
 
- Installing curb/edge concrete elements
 
- Constructing concrete access culvert.
 
- Constructing asphalt concrete channel – rigola
 
- Installing pipes for optical cable.
 
10. Mapping with horizontal and vertical signalization